Package Substation vs Switching Station: An EPC RFQ Checklist

EPC procurementPrefabricated power distributionPublished

Choose a transformer-inclusive package substation when the quoted assembly must receive medium-voltage power, step it down and hand it over at defined low-voltage terminals or feeders. Choose a prefabricated switching station when the assembly must switch, protect or route medium-voltage feeders and the main transformer is outside that scope. If another supplier is providing the transformer, give bidders its interface data and assign responsibility for the completed assembly. A common enquiry name such as compact substation or kiosk gives bidders room to price different boundaries.

Start with the project single-line diagram (SLD). Mark the incoming and outgoing handover points, identify the equipment supplied by others and assign one owner to every connection between packages. Put the marked-up SLD and the scope schedule at the same revision before comparing quotes.

Compare the three supply boundaries

Table 1 · Compare the three supply boundaries
Quote basisMain power path to show on the SLDWhat the bid must make explicit
Transformer-inclusive packageMV arrival → MV switchgear → main transformer → LV main and agreed outgoing pointIdentify the transformer and LV assembly in the equipment list. State whether the price ends at LV terminals or includes the specified outgoing feeders.
Assembly with a buyer-supplied transformerMV and LV equipment arranged around a separately procured transformerName the transformer supplier and the party responsible for compatibility, internal connections, enclosure integration and acceptance evidence. List any free-issued data or equipment required before fabrication.
MV-only prefabricated switching stationMV arrival → MV switching and protection → MV outgoing circuitsIdentify the MV feeder functions and handover terminals. List any remote transformer and downstream LV assembly under the separate scope. Show auxiliary supplies and instrument transformers where specified.

Scroll the table to read all columns. Keyboard users can focus it and use the arrow keys.

A bid that includes an LV main incomer can still exclude the outgoing breakers, cables or terminations. A bid that includes transformer space can still exclude the transformer, its installation and the connections on both sides. Ask bidders to tag each item as included, option, by others or deviation. Require a named owner and a physical handover point for each item listed as by others.

Set the project inputs before requesting a price

Table 2 · Set the project inputs before requesting a price
InterfaceBuyer inputs to issueConfirmation to request from bidders
MV arrival and departuresNominal system voltage, required equipment rating, frequency, source fault level and duration, feeder duties and quantities, cable types and entry directionProposed devices and duties, rated breaking and withstand values as applicable, interlocking, terminations included and points for external connection
Main transformer, if in scopeLoad basis, required kVA, primary and secondary voltages, transformer type, vector group, impedance, taps and site conditions as specified by the project engineerExact proposed configuration, loss and thermal data where required, protection interfaces and responsibility for MV and LV interconnections
LV output, if in scopeRequired voltage and current, fault duty, main incomer and outgoing schedule, neutral and earthing arrangementExact LV delivery point, outgoing devices included, cable or busway connection, and any separately priced feeders
Enclosure and siteLayout, available footprint, environment, flood or drainage constraints, access and removal space, cable trenches and foundation informationGeneral arrangement, dimensions, weights and lifting points, entry positions, heat-management proposal and civil works excluded
Protection, auxiliaries and controlsProtection philosophy, control-supply source, metering, remote-control and alarm points, and the owner’s communications requirementsIncluded protection and control hardware, auxiliary load and supply boundary, I/O schedule, interfaces by others and the tests for each required function

Scroll the table to read all columns. Keyboard users can focus it and use the arrow keys.

For a customer-supplied transformer, confirm the integration scope and supply responsibilities for the specific project. For a free-issued transformer, send the approved terminal positions, dimensions, mass and heat-loss information with the interface schedule. Ask who approves changes if the transformer data arrives after the kiosk drawings. If the LV panel is remote, state who supplies the secondary cable or busway, supports and termination kits. Confirm who connects the equipment to the site earthing system and where that work ends.

Separate space provision for future remote control from an installed and commissioned remote terminal unit (RTU). If the project requires SCADA, identify the points list, control supply, communication equipment and integration owner. Ask the bidder to state what will be demonstrated at the factory and what must wait for the owner’s site system.

Make quotes comparable at the handover points

Consider a project with a separate transformer purchase. One bidder shows an MV cable termination at the station wall and prices the LV board. Another shows an internal transformer connection and ends the scope at the LV main terminals. Before comparing totals, send both bidders the same SLD and request the cost and owner of the missing terminations, interconnections and outgoing feeders. The resulting scope schedule should reconcile to the drawing without any unassigned connection.

Break down site work as well. Delivery to site, unloading, lifting onto the foundation, civil works, external cabling, installation, site testing and energisation are separate milestones. State the responsible party for each, along with the drawings, records and approvals needed before handover. For outdoor or public-access sites, give bidders the access, environmental and enclosure requirements from the project documents.

Where the project specifies IEC 62271-202 for an applicable enclosed AC prefabricated substation, ask for the edition and evidence that covers the offered assembly and its configuration. Separate assembly evidence from reports for individual switchgear, transformer or LV components. Ask how any differences in the offered enclosure, arrangement or equipment are addressed. List factory acceptance tests (FAT), witness points and site acceptance tests (SAT) separately, with acceptance criteria and the party responsible for closing deviations.

In Malaysia, TNB’s compact substation guidance ties CSU siting to its system-planning and operational requirements. Use the project’s current owner or utility documents to confirm the electrical arrangement, site access, controls and acceptance process. For projects in Vietnam, Indonesia or Uzbekistan, confirm the same inputs with the relevant project owner and network operator. A specification from another project does not establish acceptance for the one being quoted.

Match the enquiry to a FUBANG product family

The FUBANG catalogue describes FBYBW as a prefabricated substation arrangement with separate compartments for switchgear, the main power transformer and LV distribution. Use this family as a starting point when the project needs the transformation step within the proposed package. Ask for a project-specific equipment list and drawings before treating any rating or included item as confirmed.

The catalogue describes FBYKW as a prefabricated switching station combining primary switching equipment and secondary protection, control and monitoring. Use this family as a starting point when the station’s main power path routes MV feeders without main step-down transformation inside the station. Confirm the protection functions, auxiliary supply and whether any remote-control equipment is installed or only space is reserved.

Review both families in the FUBANG prefabricated equipment section. For the individual MV and LV equipment requirements, see the MV switchgear selection guide and the LV switchboard procurement guide.

Send a quote request with enough detail to review

  • State the project location and owner, system voltage, station quantity, required delivery points and target delivery window.
  • Say whether the scope includes the main transformer, uses a buyer-supplied transformer or covers MV switching only.
  • Provide the feeder count and duty, any transformer and LV requirements, and the required protection and control interfaces.
  • List any owner standards, assembly evidence and witness tests requested. Identify civil works, delivery and commissioning separately.
  • Mention the revision of the available SLD, site layout and scope schedule. Summarise the project in the enquiry and arrange drawing exchange afterwards.